The proposed Oregon Avenue project schedule may be altered during the course of the project.

May 28, 2014
Start of Design Phase

August 2014
Concept Design Report

September 2014
Survey completed

September 2014
1st Public Meeting

November 2014
Preliminary Design (30%) submitted

November 2014
2nd Public Meeting

February 2015
3rd Public Meeting

April 2015
Intermediate Design (65%) submitted

May 2016
4th Public Meeting

June 2016
Final Review Submission (95%) submitted

Fall 2016
Analyzing impacts of multiple adjacent projects

November 2016
PS&E (Plans, Specifications and Estimate) submitted

Winter 2017
Re-sequencing construction phasing to avoid conflicts with concurrent construction projects within the corridor